After years of searching for a waterfront house site, we found a lot this fall on Mascoma Lake, very near our current house. This blog will follow the progress of our new timberframe house construction this year. Please enjoy and share our excitement. You can click on any picture for a larger view.
Debby and Jack

Wednesday, May 12, 2010

Large "keyed" beams in place

Progress on the timberframe was rapid last week, culminating in the placement of the largest beams on top of the great room. This required a special crane, because the beams are each 12x12 inches, and are attached to each other by the hardwood keys, or cut outs in each piece. The first figures show the crew placing the beams. The lower pictures show the frame at this stage from several perspectives, ending with Debby standing in the dining room.